Project Update (MAY 2017)

Current Projects

SUCF 231001 Rehab Exterior Envelope – Dana Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments. The project was advertised by the State University Construction Fund on April 24th. A Pre-Bid Site Meeting with interested Contractors was held May 3rd. Bids are due May 24th. It is anticipated work will begin July 2017. Construction period is expected to be 8 – 12 months.

SUCF PN 231002 Rehab Water Distribution System & Related Site Infrastructure

Project includes removal and replacement of portions of the campus’ water distribution system to correct deteriorated conditions identified in campus-wide site utility study completed October 2013 including water pump system, master water meter pit, valves, backflow preventers, water mains and individual water meters. Work is expected to begin April 2017. Water shut downs will be necessary to individual buildings during the course of the project. All water shut downs will be scheduled and notifications will be issued. The project is expected to be complete August 31, 2017.

SUCF PN 231003 Replace Roofs Cooper Service Complex & Payson Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments at the Cooper Service Complex. Removal and replacement of existing roofs, fascia, soffits and exterior lighting at Payson Hall. Work is currently ongoing at the Cooper Service Complex. Work will begin at Payson Hall May 15, 2017. The project is expected to be complete August 11, 2017.

Cooper

SUCF PN 231004 Rehab Dana Hall

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems. Design of this project has been placed on hold pending 2017 NYS Budget. Design is anticipated to move forward summer 2017.

Dana Hall

SUCF 231006 Rehab Chaney Dining Hall

Floor Plans and Renderings

Chaney Dining Center

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems.

  • Tentative Project Schedule:
    • Design 4/16 – 7/17 (Ongoing)
    • Construction 12/17 – 12/18
    • Beneficial Occupancy / Construction Completion 8/18
SUCF 231007 Site Improvements Payson Hall East

Project includes exterior renovations / replacement of pedestrian walks, stairs, rails, site lighting and stone veneer retaining walls.

  • Tentative Project Schedule:
    • Pre-Bid Site Meeting 5/8/17
    • Bid Date 5/16/17
    • Construction 6/17 – 10/17
    • Beneficial Occupancy / Construction Completion 10/2/17
SUCF 231008 Site Improvements Payson Hall North

Project includes exterior renovations / replacement of pedestrian walks, stairs, rails, site lighting and stone veneer retaining walls. Design documents are complete. Bid / Award of Construction Contract is pending 2017 NYS Budget and coordination with other projects (Rehab Water Distribution System, Replace Roof Payson Hall) within the vicinity of Payson Hall.

SUCF 231009 Replace Heating Boilers CARC

Project includes removal and replacement of existing heating boilers and flue systems. Boilers have been replaced. Work remains at roof level to replace existing flue ventilation systems. Work at roof level will be completed the week of May 15th.

SUCF 231011 Rehab Mechanical & Electrical Systems Southworth Library

Project includes removal of existing lighting and ceilings on the second floor of the library. Replacement with energy efficient lighting, lighting controls and acoustical ceilings. Project also replaces existing deficient air relief damper and installation of additional new air relief damper.

  • Tentative Project Schedule:
    • Pre-Bid Site Meeting 5/18/17
    • Bid Date 5/30/17
    • Construction 6/17 – 8/17
    • Beneficial Occupancy / Construction Completion 8/18/17
DASNY 335330 Mohawk Hall - East Wing Rehab

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems in the East Wing of Mohawk Hall. Renovation work is currently ongoing. The project is expected to be complete August 1, 2017.

DASNY 341840 Rushton Hall - East Wing Rehab

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems in the East Wing of Rushton Hall.

  • Tentative Project Schedule:
    • Design 3/17 – 6/17 (Ongoing)
    • Construction 12/17 – 8/18
    • Beneficial Occupancy / Construction Completion 8/18
L23096 Rehab Cyber Café Southworth Library

Project includes interior renovations of space, replacement of mechanical, electrical and plumbing systems supporting the current Cyber Café eatery including new restrooms located on the 1st floor and 2nd floor of Southworth Library.

  • Tentative Project Schedule:
    • Pre-Bid Site Meeting 5/18/17
    • Bid Date 6/6/17
    • Construction 6/17 – 10/17
    • Beneficial Occupancy / Construction Completion (Partial – Toilet Rooms) 8/18/17
    • Beneficial Occupancy / Construction Completion 10/6/17
L23100 Kennedy Hall Data Closet Cooling

Project includes modifications to existing ventilation systems to cool data closet spaces.

  • Tentative Project Schedule:
    • Pre-Bid Site Meeting 5/12/17
    • Bid Date 5/19/17
    • Construction 6/17 – 7/17
    • Beneficial Occupancy / Construction Completion 7/14/17
L23113 Residence Life – Emergency Lighting Upgrade

Project includes upgrade of emergency lighting systems including replacement of emergency lighting inverters in Heritage Hall, Rushton Hall, Mohawk Hall and Smith Hall.

  • Tentative Project Schedule:
    • Pre-Bid Site Meeting 5/2/17
    • Bid Date 5/15/17
    • Construction 6/17 – 7/17
    • Beneficial Occupancy / Construction Completion 7/14/17