Project Update (October 2014)

Current Projects

Campus Wide – Underground Natural Gas Piping and Site Lighting Cornell Drive (SUCF)

Project includes removal and replacement of underground natural gas piping systems, service laterals and metering.  Removal and replacement of site lighting along Cornell Drive.

  • Tentative Project Schedule:
    • 11/3/14 Design Start
    • 10/30/15 Construction Start
    • 8/12/17 Construction Completion

CARC Site & Athletic Field Improvements

Project includes additional visitor parking, site lighting, press box, baseball field and softball field dugouts, natural grass field and various field access drives.

  • Project Schedule
    • Week of July 21st – Mobilization, Erosion Control, Removals and Excavations
    • 7/28 - 9/6 – Grade for Dug Outs, Roads and Fields
    • 8/4 - 9/20 – Softball Field Dug Outs
    • 8/11 - 9/13 – Site Utilities
    • 8/18 - 10/11 – Baseball Field Dug Outs
    • 9/2 - 9/13 – Parking Lot Restoration
    • 9/2 - 11/22 – Press Box, Electrical / Mechanical Installations
    • 9/8 - 9/20 – Irrigation System
    • 9/15 - 10/4 – Finish Grade Field / Sod
    • 10/6 - 10-11 – Relocate Score Board
    • 11/10 - 11/19 – Punch List / Demobilization

Chaney Dining Hall - Rehab Portions of Dining Room

Project includes removal and replacement of windows, removal and replacement of dining room lighting, cleaning and resurfacing of dining room wood finishes, replacement of dining room floor.

  • Project Schedule
    • Removal and Replacement of Dining Room Lighting (Complete)
    • Cleaning and Resurfacing of Dining Room Wood Finishes (Complete)
    • 9/29 - 10/3 Replace Windows College Association Office Suite
    • 10/13 - 10/17 Replace Flooring College Association Office Suite
    • 11/17 - 11/21 Replace Windows Goolden Room
    • 9/24 - 10/17 Replace Dining Room Windows – South Side (Employee Entrance)
    • 10/30 - 11/14 Replace Dining Room Windows – East Side (River Side)
    • 10/20 - 10/31 Replace Dining Room Windows – North Side (Loading Dock)
    • 11/24 - 11/28 Replace Lobby Windows at Main Entrance
    • 12/22 – 1/14 (Winterterm) Replace Main Dining Room Floor
    • 12/22 – 1/14 (Winterterm) Replace Serving Line Doors
    • 12/22 – 1/14 (Winterterm) Replace Emergency Lighting Inverter
    • 12/22 – 1/14 (Winterterm) Add Additional Electrical Receptacle in Dining Room

Cooper Service Building – Replace Fuel Storage System

Project includes removal and replacement of existing underground fuel storage tanks and associated dispensing systems with new aboveground storage tanks, dispensing system and fuel management system.

  • Tentative Project Schedule
    • 8/1/14 Design Start
    • 11/1/14 Construction Start
    • 2/28/15 Construction Completion

Energy Master Plan (NYPA)

Under the direction of the New York Power Authority (NYPA), PRES Energy will conduct comprehensive energy audits of the State University of New York at Canton (SUNY Canton) designated facilities.  The purpose of these comprehensive energy audits is to identify existing conditions at each selected site, to propose measures that would increase energy efficiency of these sites and will be the basis to develop an Energy Master Plan for the selected sites.

During the development of the Energy Master Plan, PRES Energy will identify and recommend low-cost and no-cost energy efficiency opportunities; SUNY Canton may implement such measures immediately.  While industry experience has shown that SUNY Canton will save energy from such actions, PRES Energy is unable to quantify those savings until the Energy Master Plan is complete.

The comprehensive energy audits will follow guidelines for an ASHRAE Level 2 audit as documented by the American Society of Heating, Refrigerating, and Air Conditioning Engineers (ASHRAE) “Procedures for Commercial Building Energy Audits, Second Edition 2011” (ASHRAE-2011) or the most current version published by ASHRAE, with pre-described deviations.

  • Estimated Schedule
    • Kick-Off Mtg. NYPA and Pres Energy
    • Start: 1/16/14 (Complete)
  • NYSERDA Flex Tech Application
    • Start: 1/20/14 (Complete)
    • Application Delivery: 3/24/14 (Complete)
              
  • Letter Report
    • Site Visit: Week of 2/10/14 (2.5 working days on-site) (Complete)
    • Delivery: Week of 3/17/14 (Complete)
    • Customer Review: Approval by 4/18/14 (Complete)
              
  • Comprehensive Energy Audit
    • Site Visit: May/June 2014 (5-10 working days on-site) (Complete)
    • Delivery: July/August 2014
    • Customer Review: August/September 2014
  • Energy Master Plan
    • Site Visit: September/October 2014 (5-10 working days on-site)
    • Delivery: November/December 2014
    • Customer Review: Approval by January 2015

French Hall / Southworth Library (SUCF)

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments.

  • Tentative Project Schedule
    • 7/1/14 Design Start
    • 11/1/14 Bid Phase
    • 5/11/15 Construction Start
    • 8/14/15 Construction Completion

Heritage Hall - East Wing Rehab (DASNY)

Project includes removal and replacement of existing interior finishes and fixtures in the East Wing of Heritage Hall.

  • Tentative Project Schedule
    • 10/1/14 Design Start
    • 5/11/15 Construction Start
    • 8/14/16 Construction Completion

Halford Hall - Replace Electrical Service

Project includes removal and replacement of existing building electrical service.

  • Tentative Project Schedule
    • 7/1/14 Design Start
    • 10/1/14 Construction Start
    • 1/14/15 Construction Completion

Wicks Hall - Nursing Suite Renovation

Project includes partial rehabilitation of existing space on the 1st floor of Wicks Hall for Nursing Suite.

  • Tentative Project Schedule
    • 8/1/14 Design Start
    • 5/11/15 Construction Start
    • 8/14/15 Construction Completion

Wicks Hall - Rehab Stone Veneer Retaining Wall

Project includes removal and replacement of existing stone veneer on retaining wall located between Wicks Hall and Dana Hall.

  • Project Schedule
    • 9/27/14 Abate Asbestos Containing Materials (ACM)
    • 10/1 – 10/6 Mobilization
    • 10/8 – 4/20/2015 Remove / Replace Stone Veneer
    • 4/1 – 5/1 Site Restoration / Construction Completion

Wind Turbine (NYPA)

 

5 Year Capital Plan Requests (2015 – 2020)

Campus Wide - Replace Water Mains
Rehab Chaney Dining Center
Rehab Dana Hall
Rehab Payson Hall
Rehab French Hall
Upgrade Site Utilities – Various
Upgrade Mechanical, Electrical, Plumbing (MEP) - Various

Recently Completed Projects

Chaney Dining Hall - Bakery

Cook Hall - Building Rehab (SUCF) (Subject to Punch List)

Cooper Service Building Boiler Room Roof

CARC Water Main Repair

Dana Hall - Refinish Gymnasium Floor

Dana Hall - Stone Retaining Wall Repair

Miller Campus Center - Enrollment Service Center (Subject to Completion of Built – In Service Desk, Installation of Bathroom Unit Heaters, Installation of Atrium Shades, Removal and Replacement of Exterior Windows and Punch List)

Mohawk Hall - Exterior Rehab (DASNY) (Subject to Completion of Exterior Doors and Punch List)

Nevaldine South - Environmental Engineering Technology Lab (NS135)

Nevaldine South - National Grid EV Charging System

Parking Lot No. 5 (Subject to Completion of Site Lighting and Punch List)

Smith Hall - Site Rehab

Smith Hall, Mohawk Hall, Rushton Hall, Heritage Hall (Exterior Loading Dock Stairs / Asphalt Paved Parking Area)

Southworth Library - Rehab Stone Veneer Retaining Wall

 

Cooper Service Building
34 Cornell Drive