Home > Facilities Management > Planning

Project Update (October 2017)

Current Projects

SUCF 231001 Rehab Exterior Envelope – Dana Hall

The State University Construction Fund (SUCF) recently issued Notice to Proceed for the Rehab Exterior Envelope project at Dana Hall. The project includes removal and replacement of existing roofs, fascia, soffits, lighting, doors, windows, window treatments, construction of new entrance vestibules, sidewalks and landscaping. Work started this week and is anticipated to be substantially complete August 2018. Given construction activity in the vicinity of Dana Hall, Payson Hall and the Miller Campus Center, it is necessary to continue the closure of Payson Drive limiting access to emergency vehicles, service vehicles and deliveries.

Dana Hall

SUCF PN 231002 Rehab Water Distribution System & Related Site Infrastructure

Project includes removal and replacement of portions of the campus’ water distribution system to correct deteriorated conditions identified in campus-wide site utility study completed October 2013 including water pump system, master water meter pit, valves, backflow preventers, water mains and individual water meters. Work is substantially complete.

SUCF PN 231003 Replace Roofs Cooper Service Complex & Payson Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments at the Cooper Service Complex. Removal and replacement of existing roofs, fascia, soffits and exterior lighting at Payson Hall. Work is substantially complete.

Cooper

SUCF 231006 Rehab Chaney Dining Hall

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems. The State University Construction Fund (SUCF) recently authorized the advertisement for the Rehab Chaney Dining Hall project.  The project was advertised September 18, 2017 with a bid opening date scheduled October 24, 2017. Work is anticipated to begin mid December 2017 with substantial completion scheduled December 2018.

Floor Plans and Renderings

Chaney Dining Center

SUCF 231007 Site Improvements Payson Hall East

Deteriorated pedestrian walks, stairs, rails, and stone veneer retaining walls have been replaced. Substantial completion of the project is anticipated in the next few weeks. Some work (permanent handrails) will not be complete until late November 2017 due to the availability of materials.

SUCF 231008 Site Improvements Payson Hall North

Project includes exterior renovations / replacement of pedestrian walks, stairs, rails, site lighting and stone veneer retaining walls. Design documents are complete. Bid / Award of Construction Contract is pending 2018 NYS Budget.

SUCF 231009 Replace Heating Boilers CARC

Project includes removal and replacement of existing heating boilers and flue systems. Project is complete.

SUCF 231011 Rehab Mechanical & Electrical Systems Southworth Library

Project includes removal of existing lighting and ceilings on the second floor of the library. Replacement with energy efficient lighting, lighting controls and acoustical ceilings. Project also replaces existing deficient air relief damper and installation of additional new air relief damper. Work is substantially complete.

SUCF 231016 Relocate University Police Wicks Hall

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems to accommodate University Police on the ground floor of Wicks Hall. Work is anticipated to be substantially complete November 2017.

SUCF 231018 Rehab Dana Hall

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems. Design of this project has been placed on hold pending 2017 NYS Budget. Design is anticipated to move forward fall / winter 2017 - 18.

DASNY 335330 Mohawk Hall - East Wing Rehab

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems in the East Wing of Mohawk Hall. Work is substantially complete.

DASNY 341840 Rushton Hall - East Wing Rehab

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems in the East Wing of Rushton Hall. Favorable bids were received last month. Work is anticipated to begin mid December 2017 with substantial completion scheduled August 2018.

L23083 Rehab Womens Ice Hockey Locker Room

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems to accommodate Women’s Ice Hockey in the CARC. Work is anticipated to be substantially complete November 2017.

L23096 Rehab Cyber Café Southworth Library

Project includes interior renovations of space, replacement of mechanical, electrical and plumbing systems supporting the current Cyber Café eatery including new restrooms located on the 1st floor and 2nd floor of Southworth Library. Project is near completion.

L23100 Kennedy Hall Data Closet Cooling

Project includes modifications to existing ventilation systems to cool data closet spaces. Project is complete.

L23113 Residence Life – Emergency Lighting Upgrade

Project includes upgrade of emergency lighting systems including replacement of emergency lighting inverters in Heritage Hall, Rushton Hall, Mohawk Hall and Smith Hall. Project is complete.

Cooper Service Building
34 Cornell Drive
Canton, NY 13617
Phone: 315-386-7222
Fax: 315-386-7960