Project Update (August 2016)

Current Projects
SUCF PN 23218 Chaney Dining Hall – Rehab Mechanical & Plumbing Systems

Project includes removal and replacement of various mechanical and plumbing systems including replacement of failed boilers. This project is substantially complete.

SUCF PN 23234 Replace Underground Natural Gas and Site Lighting Systems

Project includes campus – wide removal and replacement of underground natural gas piping systems, service laterals and metering. Removal and replacement of site lighting along Cornell Drive. Project is near complete, work is currently ongoing. Construction completion date is 11/30/16.

SUCF PN 23235 Wicks Hall - Nursing Suite Renovation

Project includes partial rehabilitation of existing space on the 1st floor of Wicks Hall for Nursing Suite. This project is substantially complete.

SUCF PN 231001 Rehab Exterior Envelope – Dana Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments.

  • Tentative Project Schedule:
    • Design 7/15 – 11/16
    • Construction 2/17 – 11/17
    • Beneficial Occupancy / Construction Completion 11/17
SUCF PN 231002 Rehab Water Distribution System & Related Site Infrastructure

Project includes removal and replacement of portions of the campus’ water distribution system to correct deteriorated conditions identified in campus-wide site utility study completed October 2013 including water pump system, master water meter pit, valves, backflow preventers, water mains and individual water meters.

  • Tentative Project Schedule:
    • Design 6/15 – 8/16 (Complete)
    • Construction 12/16 – 9/17
    • Beneficial Occupancy / Construction Completion 9/17
SUCF PN 231003 Replace Roofs Cooper Service Complex & Payson Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments at the Cooper Service Complex. Removal and replacement of existing roofs, fascia, soffits and exterior lighting at Payson Hall. Work will begin at the Cooper Service Complex 8/16. Work at the Cooper Service Complex is expected to be completed 11/16. Work will begin at Payson Hall following Commencement 5/17 and will be completed 8/17.

  • Tentative Project Schedule:
    • Design 10/15 – 5/16 (Complete)
    • Construction 8/16 – 8/17
    • Beneficial Occupancy / Construction Completion 8/17

Cooper

SUCF PN 231004 Rehab Dana Hall

Project includes interior renovations of space, HVAC, mechanical, electrical and plumbing systems.

  • Tentative Project Schedule:
    • Design 10/15 – 11/16
    • Construction 3/17 – 8/18
    • Beneficial Occupancy / Construction Completion 8/18

Dana Hall

SUCF 231006 Rehab Chaney Dining Hall

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems.

  • Tentative Project Schedule:
    • Design 4/16 – 7/17
    • Construction 12/17 – 8/18
    • Beneficial Occupancy / Construction Completion 8/18
SUCF 231007 Site Improvements Payson Hall East

Project includes exterior renovations / replacement of pedestrian walks, stairs, rails, site lighting and stone veneer retaining walls.

  • Tentative Project Schedule:
    • Design 1/16 – 4/16 (Complete)
    • Construction 5/17 – 8/17
    • Beneficial Occupancy / Construction Completion 8/17
SUCF 231008 Site Improvements Payson Hall North

Project includes exterior renovations / replacement of pedestrian walks, stairs, rails, site lighting and stone veneer retaining walls.

  • Tentative Project Schedule:
    • Design 1/16 – 4/16 (Complete)
    • Construction 5/17 – 8/17
    • Beneficial Occupancy / Construction Completion 8/17
SUCF 231009 Replace Heating Boilers CARC

Project includes removal and replacement of existing heating boilers and flue systems.

  • Tentative Project Schedule:
    • Design 4/16 – 8/16
    • Construction 10/16 – 11/16
    • Beneficial Occupancy / Construction Completion 11/16
DASNY 320030 Heritage Hall - East Wing Rehab

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems in the East Wing of Heritage Hall.  This project is substantially complete.

DASNY 335330 Mohawk Hall - East Wing Rehab

Project includes interior renovations of space, replacement of HVAC, mechanical, electrical and plumbing systems in the East Wing of Mohawk Hall.

  • Tentative Project Schedule:
    • Design 4/16 – 8/16 (Complete)
    • Construction 12/16 – 8/17
    • Beneficial Occupancy / Construction Completion 8/17
PN L23049 Reconstruct Parking Lot No. 3 (Heritage Hall)

Project includes removal and replacement of asphalt paved parking lot near Heritage Hall including curbs, walks, storm water management features and site lighting. This project is substantially complete.

PN L23050 Reconstruct Parking Lot No. 8 (French Hall)

Project includes removal and replacement of asphalt paved parking lot near French Hall including curbs, walks, storm water management features and site lighting. This project is substantially complete.

L23068 Energy Master Plan (NYPA)

Under the direction of the New York Power Authority (NYPA), PRES Energy will conduct comprehensive energy audits of the State University of New York at Canton (SUNY Canton) designated facilities. The purpose of these comprehensive energy audits is to identify existing conditions at each selected site, to propose measures that would increase energy efficiency of these sites and will be the basis to develop an Energy Master Plan for the selected sites.

During the development of the Energy Master Plan, PRES Energy will identify and recommend low-cost and no-cost energy efficiency opportunities; SUNY Canton may implement such measures immediately. While industry experience has shown that SUNY Canton will save energy from such actions, PRES Energy is unable to quantify those savings until the Energy Master Plan is complete.

The comprehensive energy audits will follow guidelines for an ASHRAE Level 2 audit as documented by the American Society of Heating, Refrigerating, and Air Conditioning Engineers (ASHRAE) “Procedures for Commercial Building Energy Audits, Second Edition 2011” (ASHRAE-2011) or the most current version published by ASHRAE, with pre-described deviations.

  • Estimated Schedule
    • Kick-Off Mtg. NYPA and Pres Energy (Complete)
    • NYSERDA Flex Tech Application (Complete)
    • Letter Report (Complete)     
    • Comprehensive Energy Audit (Ongoing)
    • Energy Master Plan (Ongoing)
L23072 Construction of New Storage Building & Renovation of Existing Storage Building

Project includes construction of new storage building, replacement of exterior envelope of existing storage building and site improvements located near the Convocation Athletic Recreation Center (CARC).  This project is complete.

M23585 Renovation of Wicks Hall Entrance (Parking Lot 5)

Project includes removal and replacement of interior and exterior entrance doors to Wicks Hall from Parking Lot No. 5 including interior and exterior lighting systems, card access systems, finish floors, walls and ceilings.  Work is expected to begin the week of September 6th with completion scheduled October 28th.  In order to safely complete the project, a temporary entrance from Parking Lot No. 5 will be established.  At all times, the existing exit will be maintained in the event of an emergency.

 