Home > Facilities Management > Planning

Project Update (October 2015)

Current Projects

SUCF PN 23207 French Hall / Southworth Library – Rehab Windows, Roofs, Fascia & Soffits

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments. Project is substantially complete, subject to punch list.

  • Tentative Project Schedule to complete Interior Renovations: TBD

SUCF PN 23218 Chaney Dining Hall – Rehab Mechanical & Plumbing Systems

Project includes removal and replacement of various mechanical and plumbing systems including replacement of failed boilers.

SUCF PN 23230 CARC Site & Athletic Field Improvements

Project includes additional visitor parking, site lighting, press box, baseball field and softball field dugouts, natural grass field and various field access drives. Project is complete.

SUCF PN 23232 Cooper Service Building – Replace Fuel Storage System

Project includes removal and replacement of existing underground fuel storage tanks and associated dispensing systems with new aboveground storage tanks, dispensing system and fuel management system.

  • Tentative Project Schedule
    • 9/28/15 – 10/2/15 Submittals, Mobilization, Install Temporary Fuel Storage Tanks
    • 10/5/15 – 10/9/15 Demolition
    • 10/12/15 – 10/30/15 Concrete Foundations and Electrical
    • 11/2/15 – 11/6/15 Site / Finish Work
    • Project Shutdown Period
    • 1/4/16 – 1/15/16 Install New Fuel Storage Tanks
    • 1/11/16 – 1/15/16 Remove Temporary Fuel Storage Tanks
    • 1/18/16 – 1/22/16 Demobilization, Project Closeout

SUCF PN 23233 Wicks Hall - Rehab Stone Veneer Retaining Wall

Project includes removal and replacement of existing stone veneer on retaining wall located between Wicks Hall and Dana Hall. Project is complete.

 

SUCF PN 23234 Replace Underground Natural Gas and Site Lighting Systems

Project includes removal and replacement of underground natural gas piping systems, service laterals and metering. Removal and replacement of site lighting along Cornell Drive.

  • Tentative Project Schedule:
    • Design 10/29/14 – 8/27/15
    • Construction 12/11/15 – 12/12/16
    • Beneficial Occupancy / Construction Completion 12/12/16

SUCF PN 23235 Wicks Hall - Nursing Suite Renovation

Project includes partial rehabilitation of existing space on the 1st floor of Wicks Hall for Nursing Suite.

  • Tentative Project Schedule:
    • Advertise 11/16/15
    • Pre-Bid Conference 11/24/15
    • Bid Opening 12/8/15
    • Notice of Award / Executed Contract 12/31/15
    • Construction Start 1/18/16
    • Construction Completion 8/5/16

SUCF PN 231001 Rehab Exterior Envelope – Dana Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments.

  • Tentative Project Schedule:
    • Design 7/2/15 – 4/25/16
    • Construction 8/4/16 – 9/8/17
    • Beneficial Occupancy / Construction Completion 9/8/17

SUCF PN 231002 Rehab Water Distribution System & Related Site Infrastructure

Project includes removal and replacement of portions of the campus’ water distribution system to correct deteriorated conditions identified in campus-wide site utility study completed October 2013 including water pump system, master water meter pit, valves, backflow preventers, water mains and individual water meters.

  • Tentative Project Schedule:
    • Design 6/10/15 – 6/23/16
    • Construction 10/20/16 – 12/20/17
    • Beneficial Occupancy / Construction Completion 12/20/17

SUCF PN 231003 Replace Roofs Cooper Service Complex & Payson Hall

Project includes removal and replacement of existing roofs, fascia, soffits, exterior lighting, doors, windows and interior window treatments.

  • Tentative Project Schedule:
    • Design 9/24/15 – 3/21/16
    • Construction 6/29/16 – 12/30/16
    • Beneficial Occupancy / Construction Completion 12/30/16

SUCF PN 231004 Rehab Dana Hall

Project includes interior renovations of space, HVAC, mechanical, electrical and plumbing systems.

  • Tentative Project Schedule:
    • Design 10/1/15 – 9/28/16
    • Construction 1/12/17 – 8/1/18
    • Beneficial Occupancy / Construction Completion 8/1/18

DASNY PN 320030 Heritage Hall - East Wing Rehab

Project includes removal and replacement of existing interior finishes and fixtures in the East Wing of Heritage Hall.

Phase I – Asbestos Abatement. Project is complete.
Phase II – New Polished Concrete Floors. Project is complete.
Phase III – General Construction, Interior Rehab

  • Tentative Project Schedule:
    • 10/29/15 Advertise
    • 11/3/15 Pre-Bid Conference
    • 11/19/15 Bid Opening
    • 12/31/15 Notice of Award / Executed Contract
    • 8/5/16 Construction Completion

PN L23049 Reconstruct Parking Lot No. 3 (Heritage Hall)

Project includes removal and replacement of asphalt paved parking lot near Heritage Hall including curbs, walks, storm water management features and site lighting.

  • Tentative Project Schedule:
    • 3/29/16 Advertise
    • 4/12/16 Pre-Bid Conference
    • 4/19/16 Bid Opening
    • 5/3/16 Notice of Award / Executed Contract
    • 5/17/16 Construction Start
    • 8/5/16 Construction Completion

PN L23050 Reconstruct Parking Lot No. 8 (French Hall)

Project includes removal and replacement of asphalt paved parking lot near French Hall including curbs, walks, storm water management features and site lighting.

  • Tentative Project Schedule:
    • 3/29/16 Advertise
    • 4/12/16 Pre-Bid Conference
    • 4/19/16 Bid Opening
    • 5/3/16 Notice of Award / Executed Contract
    • 5/17/16 Construction Start
    • 8/5/16 Construction Completion

PN L23060 PV Solar Development Project

Project includes development of a remote net-metered ground mounted solar photovoltaic array of 2.0 MW (AC) capacity on properties owned by Hemlock Acres, LLC located on State Highway 68 in the Town of Canton, St. Lawrence County, New York.

  • Tentative Project Schedule:
    • 7/28/15 Letter of Intent (Complete)
    • 11/4/15 Executed Contract
    • 12/14/15 Design Development
    • 4/11/16 Construction Start
    • 8/15/16 Substantial Completion, Project Closeout
    • 9/13/16 Interconnection, Permission to Operate

PN L23072 Construction of New Storage Building & Renovation of Existing Storage Building

Project includes construction of new storage building and replacement of exterior envelope of existing storage building located near the Convocation Athletic Recreation Center (CARC).

  • Tentative Project Schedule:
    • 9/25/15 Advertise (Complete)
    • 10/15/15 Pre-Bid Conference
    • 10/28/15 Bid Opening
    • 11/12/15 Notice of Award / Executed Contract
    • 4/15/16 Construction Completion

Energy Master Plan (NYPA)

Under the direction of the New York Power Authority (NYPA), PRES Energy will conduct comprehensive energy audits of the State University of New York at Canton (SUNY Canton) designated facilities. The purpose of these comprehensive energy audits is to identify existing conditions at each selected site, to propose measures that would increase energy efficiency of these sites and will be the basis to develop an Energy Master Plan for the selected sites.

During the development of the Energy Master Plan, PRES Energy will identify and recommend low-cost and no-cost energy efficiency opportunities; SUNY Canton may implement such measures immediately. While industry experience has shown that SUNY Canton will save energy from such actions, PRES Energy is unable to quantify those savings until the Energy Master Plan is complete.

The comprehensive energy audits will follow guidelines for an ASHRAE Level 2 audit as documented by the American Society of Heating, Refrigerating, and Air Conditioning Engineers (ASHRAE) “Procedures for Commercial Building Energy Audits, Second Edition 2011” (ASHRAE-2011) or the most current version published by ASHRAE, with pre-described deviations.

  • Estimated Schedule
    • Kick-Off Mtg. NYPA and Pres Energy (Complete)
    • NYSERDA Flex Tech Application (Complete)
    • Letter Report (Complete)     
    • Comprehensive Energy Audit (Ongoing)
    • Energy Master Plan (Ongoing)
 

Cooper Service Building
34 Cornell Drive
Canton, NY 13617
Phone: 315-386-7222
Fax: 315-386-7960