Home > Facilities Management > Planning

Project Update

Current Projects

CARC Site & Athletic Field Improvements

  • Project Schedule
    • Week of July 21st – Mobilization, Erosion Control, Removals and Excavations
    • 7/28 - 9/6 – Grade for Dug Outs, Roads and Fields
    • 8/4 - 9/20 – Softball Field Dug Outs
    • 8/11 - 9/13 – Site Utilities
    • 8/18 - 10/11 – Baseball Field Dug Outs
    • 9/2 - 9/13 – Parking Lot Restoration
    • 9/2 - 11/22 – Press Box, Electrical / Mechanical Installations
    • 9/8 - 9/20 – Irrigation System
    • 9/15 - 10/4 – Finish Grade Field / Sod
    • 10/6 - 10-11 – Relocate Score Board
    • 11/10 - 11/19 – Punch List / Demobilization

Chaney Dining Hall - Bakery

  • Work to rehab Chaney Dining Hall bakery scheduled 6/2 – 8/8.

Chaney Dining Hall - Rehab Portions of Dining Room

  • Chaney Dining Hall Rehab (link in development)

Cook Hall - Building Rehab (SUCF)

Dana Hall - Refinish Gymnasium Floor

  • Work to refinish Dana Hall gymnasium floor scheduled 6/23 – 8/1.

» Energy Master Plan (NYPA)

» Mohawk Hall - Exterior Rehab (DASNY)

Parking Lot No. 5

  • Project Schedule:
    • Friday, June 27th - Close Parking Lot No. 5 End of Business
    • Week of June 30th – Mobilization
    • Week of July 7th – Erosion Control, Removals and Excavations
    • Week of July 14th – Installation Stone Sub-Base, Curb and Sidewalks
    • Week of July 21st – Pavement Binder
    • Week of August 11th – Pavement Top, Striping, Signage, Topsoil and Seeding
    • Monday, August 18th – Open Parking Lot No. 5 Begin of Business
  • Between June 28th and August 17th, it will be necessary for those currently using Parking Lot No. 5 to utilize Parking Lot No. 3.

Smith Hall, Mohawk Hall, Rushton Hall, Heritage Hall

  • Work to replace exterior loading dock stairs and restore asphalt paved parking areas behind each of the residence halls scheduled 7/7 – 8/29.

Wind Turbine (NYPA)

 

Planned Projects

Cooper Service Building  - Replace Fuel Storage System

CREST Building - Replace Electrical Service

French Hall / Southworth Library - Replace Windows (SUCF)

Heritage Hall - East Wing Rehab (DASNY)

Site - Replace Natural Gas Mains (SUCF)

Site - Replace Water Mains (SUCF)

Site - Replace Site Lighting Cornell Drive

Wicks Hall - Rehab Stone Veneer Retaining Wall

 

Recently Completed Projects

Cooper Service Building Boiler Room Roof

CARC Water Main Repair (Subject to Asphalt Replacement)

Dana Hall - Stone Retaining Wall Repair

Miller Campus Center - Enrollment Service Center

Nevaldine South - Environmental Engineering Technology Lab (NS135)

Nevaldine South - National Grid EV Charging System

Smith Hall - Site Rehab

Southworth Library - Rehab Stone Veneer Retaining Wall

 

Cooper Service Building
34 Cornell Drive
Canton, NY 13617
Phone: 315-386-7222
Fax: 315-386-7960