Project Schedule

Contract Execution - 1/14/13


Phase 1
  1. Site Assessment - 1/29/13 - 3/25/13 - COMPLETE
  2. SEQR (By Others) - 3/4/13 - 8/9/13
  3. 30% Design Submittal - 3/26/13 - 6/11/13 - COMPLETE
  4. Public Outreach #1- 4/16/13
  5. Balloon Float & Visual Assessment - 4/17/13 - 4/23/13 - COMPLETE
  6. Avian & Wildlife Study - 4/29/13 - 10/25/13 - COMPLETE
  7. Cultural & Archaeological Studies - 5/15/13 - 6/4/13 - COMPLETE
  8. Ambient Study & Acoustic Report - 5/20/13 - 6/21/13 - COMPLETE
  9. NYPA Review & Comment - 6/12/13 - 7/16/13 - COMPLETE
  10. 60% Design Submittal - 7/17/13 - 8/6/13 - COMPLETE
  11. Public Outreach #2 - 7/17/13
  12. NYPA Review & Comment - 8/7/13 - 9/10/13
  13. 90% Design Submittal - 9/11/13 - 10/1/13
  14. NYPA Review & Comment - 10/2/13 - 11/5/13
  15. Public Outreach #3 - 11/11/13
  16. Final Design Acceptance - 11/6/13 - 11/13/13

CIC Execution - 11/14/13 - 3/6/15


Phase 2
  1. Turbine Purchasing & Shipping - 2/20/14 - 9/19/14
  2. Secure Site-Mobilize - 2/20/14 - 3/5/14
  3. Utility Upgrades (Others) - 3/3/14 - 4/25/14
  4. Construct Access Drive - 3/6/14 - 5/28/14
  5. Construct Foundation - 5/29/14 - 6/25/14
  6. Underground Electrical - 6/26/14 - 7/23/14
  7. Turbine Delivery - 9/22/14 - 10/17/14
  8. Turbine Erection - 10/20/14 - 10/31/14
  9. Tower Elect/Com - 11/3/14 - 11/28/14
  10. Start Up/Commission - 12/1/14 - 12/12/14
  11. Commercial Operation Begin & Break-In Period - 12/15/14 - 3/6/15

 

 

 